On Friday, July 9, 2021, it was announced that this proposed 1.1 GW gas plant was cancelled. NOVI Energy, the developer of this project that officially began in 2016, issued the following statement:

 

"NOVI Energy cares deeply about the communities it serves and the affordable, reliable power facilities it helps build. After taking feedback from the community and assessing the changing market, NOVI Energy has decided not to pursue the C4GT power plant."

​

The Richmond Times Dispatch story that broke this news reported "The move was welcomed by people in the county who say they don’t want more fossil fuel pollution. Opponents say local and state officials haven’t been transparent about the proposal and a plan for a second plant a mile away."

 

C5 will continue to fight the Chickahominy Gas Plant, that second plant, and is grateful for the community members who've advocated against C4GT with us!

C4GT Air Permit

The following permit was issued by the DEQ on April 26, 2018. 

C4GT Engineering Analysis

Engineering Analysis done by the DEQ and published on March 6, 2018.

C4GT Extension

The extension gave by the DEQ and published on June 4, 2019

C4GT Case Document Cover Sheet

The case document cover sheet was issued March 1, 2019

C4GT Virginia Water Protection Permit

This permit was issued to C4GT by DEQ August 2017

table plants_edited.jpg

Location C4GT Plant: 3001 Roxbury Rd, Charles City VA

C4GT map.png